15 & 16 October 2019
The 24th Project Committee (PC#24) was held at Rokkasho Broader Approach Site on October 15 and 16. The project status and achievements were presented as well as the outlook from phase B+ onward. The main update topics discussed were:
- RF system improvement
- Phase B milestone beam perveance record
- Beam Dump installation resumed
- Phase B end and the maintenance period start
- Technical difficulties
- Next objectives towards continuous wave operation
- Objectives of High Energy Beam Transport line and Beam Dump validation
- Long-term improvement actions
- Preparation of the Medium Energy Beam Transport extension line
- Status of superconducting solenoids procurement for the SRF Linac Cryomodule
- Preparatory status for the clean room assembly of the Cryomodule
The action plan for 2020 was presented for installation, maintenance and operation.