15 & 16 October 2019
The 24th Project Committee (PC#24) was held at Rokkasho Broader Approach Site on October 15 and 16. The project status and achievements were presented as well as the outlook from phase B+ onward. The main update topics discussed were:
- RF system improvement
- Phase B milestone beam perveance record
- Beam Dump installation resumed
- Phase B end and the maintenance period start
- Technical difficulties
- Next objectives towards continuous wave operation
- Objectives of High Energy Beam Transport line and Beam Dump validation
- Long-term improvement actions
- Preparation of the Medium Energy Beam Transport extension line
- Status of superconducting solenoids procurement for the SRF Linac Cryomodule
- Preparatory status for the clean room assembly of the Cryomodule
The action plan for 2020 was presented for installation, maintenance and operation.

The PC members near the clean room Inside the RF area