Weekly LIPAc highlights (1/March-5/March)

Global Alignment survey

The realignment of the second solenoid magnet (SOL2) of the LEBT (Low Energy Beam Transport) to the entrance of the RFQ was completed this week.

Realignment of the SOL2 magnet of the LEBT

Injector

Following the decision taken earlier in February at management level, at the beginning of this week (before starting the realignment work) the Plasma Electrode (PE) currently installed in the Injector, with a diameter of 11mm, was changed with a PE of 6mm. Also, in the LEBT the chopper was reinstalled after the refurbishment and checkout tests performed in the last months.

Radio Frequency (RF) System and RFQ cavity                                                             

The start-up of the RF system with the calibration of the LLRF (Low Level RF) and the RF chains continued. RF noise issues are currently investigated for flow meters, PSYS-LLRF interface and other interlock signals. During injection in the RFQ cavity 150us/100 Hz @ 132 kV (D+ level) were achieved. The training on the operation of the Solid State Power Amplifiers (SSPA) for the MEBT (Medium energy Beam Transport) bunchers was completed.

Test preparations in front of RF-RFQ modules in RF area

Disclaimer: the information reported is not meant to be technically complete and doesn’t cover all the activities currently carried out on LIPAc. 

Weekly LIPAc highlights (22/Febuary-26/February)

Global Alignment survey

Additional alignment survey has been completed and the results shared and thoroughly discussed. The realignment of the second solenoid magnet (SOL2) of the LEBT (Low Energy Beam Transport) to the entrance of the RFQ will be performed starting next week. The correction of the alignment between the end of the RFQ and the beginning of the MEBT (Medium Energy Beam Transport) will be performed in the next maintenance period and before starting high duty beam operation. Correction of the mismatch between RFQ and MEBT, considering the size of the RFQ, is challenging and laborious (detailed procedures will be prepared).

Radio Frequency (RF) System and RFQ cavity                                                             

The start-up of the RF system with the calibration of the LLRF (Low Level RF) and the RF chains continued. The installation of Low Pass Filters into the PSYS-LLRF (Protection System – Low Level RF) interface boards was completed. During first RF injections @ 132 kV, D+ level, noise issues on PSYS interlock and water flow meter appear when pulse length exceeds 250us and are under investigation. Check-out of the RFQ cavity with RF injection is pending the completions of these activities.

Beam Dump

As part of the BD skid commissioning, the update of the PLC software for the BD cooling skid is on-going with remote support by CIEMAT.

Disclaimer: the information reported is not meant to be technically complete and doesn’t cover all the activities currently carried out on LIPAc. 

Weekly LIPAc highlights (15/Febuary-19/February)

Global Alignment survey

Additional data for the alignment survey have been collected with highest priority to complete the missing points and improve the accuracy of measurements. The attention is focused in the portions at the end of RFQ and beginning of MEBT. In parallel to the analyses of the data, a procedure to eventually realign those parts is under investigation.

Radio Frequency (RF) System and RFQ cavity                                                             

The start-up of the RF system with the calibration of the LLRF (Low Level RF) and the RF chains continued. The focus was the calibration of the Anode boxes and the installation of Low Pass Filters into the PSYS-LLRF interface boards. Check-out of the RFQ cavity with RF injection is pending the completions of these activities.

Beam Dump

As part of the BD skid commissioning, the update of the PLC software for the BD cooling skid has started with remote support by CIEMAT.

Control System

The Control System team is coordinating the work and ensuring the support of all the teams to complete the preparation of the new Central Control Room for the next beam commissioning and conditioning.

Disclaimer: the information reported is not meant to be technically complete and doesn’t cover all the activities currently carried out on LIPAc. 

Weekly LIPAc highlights (1/Febuary-5/February)

Global Alignment survey

The analyses of the data collected during the global alignment survey of the entire LIPAc accelerator has been completed. Additional measurements of the first RFQ module and of one HEBT magnet are on-going to assess if realignment is necessary.

Radio Frequency (RF) System and RFQ cavity                                                             

The start-up of the RF system with the calibration of the LLRF (Low Level RF) and the RF chains continued this week. The behaviour of the RF cavity during first trials of RF injection is checked as a part of training program.

HEBT (High Energy Beam transport) commissioning

The backup PS for the dipole magnet was delivered on-site and its installation started.

Beam Dump

As part of the BD skid commissioning, the automatic pressure adjustment of the skid using the expansion tank was successfully performed.

Disclaimer: the information reported is not meant to be technically complete and doesn’t cover all the activities currently carried out on LIPAc. 

Weekly LIPAc highlights (25/Janurary-29/January)

Global Alignment survey

The global alignment survey of the entire LIPAc accelerator from ion source to beam dump cartridge has been completed. The large amount of data recorded is being analysed to assess if further measurements or actions are necessary.

RFQ vacuum system

The RFQ nominal vacuum has been resumed smoothly.

Radio Frequency (RF) System   

The start-up of the RF system with the calibration of the LLRF (Low Level RF) and the RF chains including the debugging started this week. The activity focused on the calibration of the 8 RF chains. Next week the plan is to finalize the calibrations, to check the PSYS interlock after the calibration and check the upgraded anode box. Also, some pending software modifications and LCS updates will be performed (activities for which the RF system ON is needed).

Beam Dump

The installation of the planned upgrade in the deaeration loop (oxygen control loop) of the Beam Dump was completed and water circulation is in preparation.

Disclaimer: the information reported is not meant to be technically complete and doesn’t cover all the activities currently carried out on LIPAc. 

Weekly LIPAc highlights (18/Janurary-22/January)

Global Alignment survey

The main activity in the vault in the first part of January has been the global alignment survey of the entire LIPAc accelerator from ion source to beam dump cartridge. The alignment survey has been performed to check that all accelerator components are positioned within the acceptance tolerances. It is the first time that the survey is performed for all the components along the line: as it was observed during the preliminary inspections, this increases the complexity of this laborious activity because the visibility and accessibility of the fiducials markers (i.e. the points of reference for the measurements) is limited. The survey will be completed by the end of this week.  

Laser trackers in position during the alignment survey in the vault.

Radio Frequency (RF) System

The key upgrade of the PYS-LLRF interface to improve the time response of the fast interlock has been propagated to all the RF-RFQ modules. Start-up of the RF system with LLRF (Low Level RF) calibration and RFPS calibration and debugging is planned next week, targeting beginning of February to start RF injection in the RFQ cavity.

RFQ vacuum system

After the planned stop at the end of the year, and in preparation of the RFQ cavity conditioning, the RFQ nominal vacuum will be resumed immediately after completion of the alignment survey, starting all the cryopump groups.

Beam Dump

The installation of the planned upgrade in the deaeration loop (oxygen control loop) of the Beam Dump is ongoing.

Disclaimer: the information reported is not meant to be technically complete and doesn’t cover all the activities currently carried out on LIPAc. 

Weekly LIPAc highlights (14/December-18/December)

Facility Inspection

On Wednesday 16th December the facility inspection was completed successfully. The Injector operation was very stable at 50% duty cycle (dc) and 100mA of total extracted current from deuterium plasma. A positive notification of the acceptance of the inspection is expected shortly. To be noted that this facility inspection could be the last one until completion of the planned LIPAc operation.

HEBT (High Energy Beam Transport) commissioning

This week more remote sessions with CIEMAT support took place for the commissioning of the different Beam Instrumentation equipment installed in the HEBT line (SEM grid, Slits, Faraday Cup).

Beam Dump

The installation of the planned upgrade in the deaeration loop (oxygen control loop) of the Beam Dump continued all the week.

Vacuum systems and ancillaries

RFQ and HEBT cryopump groups have been safely stopped (the RFQ cavity is still pumped by one turbomolecular pump, the HEBT is kept in static vacuum). The same will be done for their cooling skids. The systems are maintained in a safe situation because of several maintenance activities planned during the winter break on compressed air system and on common skids.

Global Alignment survey

The preparation of the global alignment survey of the LIPAc continued and the work in the vault will start this week.

Disclaimer: the information reported is not meant to be technically complete and doesn’t cover all the activities currently carried out on LIPAc. 

Weekly LIPAc highlights (7/December-11/December)

Injector conditioning

The Injector operation continued this week at 50% duty cycle (d.c.) and 100mA of total extracted current from deuterium plasma. The beam was very stable and the ramp-up time to the target dc could be improved.  The target performance for the facility inspection (50%dc @100mA) was confirmed. On Friday afternoon a self-imposed inspection was performed with measurements of radiation level while the injector operates at 50%dc @100mA. The facility inspection is scheduled next week, on 16th December.

Radio Frequency (RF) System

After the start-up of the entire RF system last week, a few additional actions to improve the stability of the system were identified. Next week the final tetrode of chain 2A will be extracted for high voltage conditioning. In parallel the key upgrade of the PYS-LLRF interface to improve the time response of the fast interlock is ongoing. The performance checks and further improvement were completed on the RF module 4 and the RF team target to propagate the modification to all the modules by mid of January. RF injection in the RFQ should resume in the second half of January.

HEBT (High Energy Beam Transport) commissioning

This week was again very dense of remote sessions with great support from CIEMAT. Efforts were dedicated to commission the different Beam Instrumentation equipment installed in the HEBT line (SEM grid, Slits, Faraday Cup) and to solve setting issues with two power supplies of two quadrupoles magnets. Presently all Power Supplies (apart the Dipole Power supply for which urgent countermeasures are being taken) of HEBT magnets are working properly and correctly set-up. 

Beam Dump

The installation of the planned upgrade in the deaeration loop (oxygen control loop) of the Beam Dump started this week and it is planned to last until 18 December.

Global Alignment survey

The planned global alignment survey of the LIPAc has been anticipated to start in December after the facility inspection. Preparation of instrumentation, training and inspection in the vault were carried out this week.

Disclaimer: the information reported is not meant to be technically complete and doesn’t cover all the activities currently carried out on LIPAc. 

Weekly LIPAc highlights (30/November-4/December)

Injector conditioning

The Injector operation continued this week: the duty cycle (dc) was increased up to 50% with a very stable beam and 100mA of total extracted current from deuterium plasma. The target performance for the facility inspection (50%dc @100mA) has been reached well ahead of schedule. Next week (last week of operation before the facility inspection, scheduled for 16th December) the efforts will concentrate on decreasing the ramp-up time (it currently takes a few hours to ramp-up the injector to 50% of duty cycle).

Screenshot of the injector oscilloscope on 03 December:

  • Duty cycle: 50% (80ms/160ms)
  • Total extracted current (red, Iext): ~100 mA
  • Yellow: Faraday cup signal (I_FC)
  • Blue: Current of repeller PS (I_repeller)
  • Green: Voltage of repeller PS (V_repeller)

Radio Frequency (RF) System and RFQ cavities (Radio Frequency Quadrupoles)

This week the RFQ nominal vacuum conditions were resumed switching on all the cryo pumping groups.

The entire RF system has been progressively started to validate the upgrades implemented in a part of the RF chains and to train QST personnel on the entire start-up process (calibration of the RF chains, RF-RFQ interfaces checks).  This afternoon we had successfully injected RF in the RFQ cavity!

Once completed the on-going tests and the upgrades validated, the modifications will be propagated in all the modules starting from next week, as soon as the RF system will be stopped. The target being to resume now the RF-RFQ conditioning in the second half of January.

HEBT (High Energy Beam Transport) commissioning

This week was very dense of remote sessions with great support from CIEMAT. The efforts focused on the commissioning and debugging of software for the different Beam Instrumentation equipment installed in the HEBT (SEM grid, Slits, Faraday Cup).

FMEA analyses

The Failure Mode and Effect Analysis (FMEA) of the LIPAc was initiated early this year with the objective to reduce hazards during its maintenance and operation phases. After 2 training sessions, the FMEA was discussed identifying hazards subsystem by subsystem during 26 working sessions. As a result, 59 actions and recommendations were proposed to improve the safety of the project and were included in the final report that was shared this week with the FMEA working group and group coordinators. The identified critical actions will be implemented as prerequisite before resuming the LIPAc beam operation. All the groups including the EU experts participated to this activity, so we can clearly call this achievement an all-hands work resulting from the collaboration of Japan and Europe within the Broader Approach.

Disclaimer: the information reported is not meant to be technically complete and doesn’t cover all the activities currently carried out on LIPAc. 

Weekly LIPAc highlights (23-27/November)

Injector conditioning

The Injector operation continued this week: the duty cycle was increased up to 30% with a very stable beam and 100mA of total extracted current from deuterium plasma. The vault will now be predominantly closed to continue the conditioning of the Injector in preparation of the facility inspection. The target performances for the facility inspection (planned on December 16) is 50% duty cycle at 100 mA of total extracted current.

Screenshot of the injector oscilloscope on 25 November:

  • Duty cycle: 31.2% (50ms/160ms)
  • Red: Total extracted current (Iext)
  • Yellow: Faraday cup signal (I_FC)
  • Blue: Current of repeller PS (I_repeller)
  • Green: Voltage of repeller PS (V_repeller, -4.5 kV)

RadioFrequency (RF) System

The RF team concluded several important activities this week:

  • The issue on the High Voltage Power supply 3A (HVPS3A) was solved with continuous remote support from JEMA.
  • The upgrade of the PSYS (Protection system) interlock was completed and installed on one RF module. The modification of the threshold levels of PSYS VSWR (Voltage Standing Wave Ratio) card were completed on the same module.
  • The anode box upgrade to decrease the overheating at the circuit board was successfully implemented in one module.

The plan is to start next week the entire RF system to validate the upgrades implemented in a part of the RF chains and to train QST personnel on the entire start-up process. Once the upgrades validated, the RF system will be stopped and the upgrades extended to all the modules.