7th LIPAc Technical Meeting

Group picture LTM07
LTM07 – Participants, Rokkasho – Japan (Group picture)

   

The 7th LIPAc Technical Meeting (LTM07) was held at Rokkasho, BA site Fusion Research Center (Japan) from 15th to 17th June 2015, and on the following two days Satellite meetings with more detailed technical discussions were held.

More than 40 experts from CEA (Saclay, France), INFN (Legnaro, Italy), JAEA (Rokkasho, Japan), CIEMAT (Madrid, Spain), F4E (Garching, Germany)and the IFMIF/EVEDA Project Team attended the meeting with additional European experts contributing remotely by videoconference.

Attendees LTM07 (partial view)
Partial view of the attendees LTM07

 

The technical information that was presented at the meeting highlighted the significant progress achieved for the various components since the last LTM06 in November 2014.

A particular highlight was the positive results that are presently obtained from the Injector commissioning as shown by the operation leader, Yoshikazu Okumura.

 

 

 

The main outcomes presented during this meeting are listed below:

Injector

Injector commissioning
Injector commissioning phase A1.2, Emittance measurement

The Injector commissioning resumed on April 22nd with the objective to complete the phase A1.2 (H+ beam, energy 50keV,variation d.c.,UIE,Itot) including the characterization and optimization of the proton beam. Performances of 100kV/155mA @ 20% duty cycle were reached during this campaign, allowing optimization of the beam emittance. Continuous wave (CW) operation was also tested successfully at 120 mA/100 kVeV, with 650 W RF power and SCCM gas flow rate.

The next important step is expected in July with the proposed start of deuterium operation (phase A1.3) after the Facility inspection by Radiation Authority.

 

 

 

Electrical platform
LIPAc Electrical platform

RF power systems

Installation of transformers and the HV breakers on the electrical platform has started with JAEA contractor NKK. The contract for the remaining cable trays will be launched soon.

The delivery of the HVPS and RF power system for the RFQ is expected by the end of July 2015 at Rokkasho and its installation will take place upon its arrival.

 

 

 

 

 

  • The RFQ super modules are nearing completion at INFN Legnaro (Italy) and will be shipped in December 2015 after the final acceptance test at Legnaro in November 2015. Cooling skid, piping and accessories will be shipped by the end of September 2015. The remaining components will be shipped to Rokkasho by February 2016.
  • MEBT: much work has been completed in the last months to finish the manufacturing and the tests of the main components and auxiliaries. CIEMAT continue to push to have the beamline integrated for test by the end of this summer, with the aim to have the MEBT delivered to Rokkasho at the beginning of 2016.
  • The LPBD detailed design is on going, was showed in the presentation its readiness for construction. Details for its cooling system were also discussed during the LTM.
  • The SRF Linac design is completed and manufacturing contracts for the critical components have been placed. The licensing activities are on-going.
  • The D-Plate is almost completed and will be ready for shipment by November 2014. Some activities of alignment of the components need to be confirmed by ensuring the reproducibility of the ideal accuracy expected.
  • The HEBT and Beam Dump main components designs partially completed as already discussed in the previous LTM06 held last November 2015. Technical specifications are nearing completion and several manufacturing contracts have been launched
  • Writing of the beam dump cooling system specification will start soon
Controlarea PPS
Control room PPS, main control console with monitors

 

  • PPS-MPS,are now operational for injector commissioning. However, some modifications will be necessary for the next phase, especially with respect to the integration into the CCS, which is considered as an important milestone;

 

 

A site visit of the Accelerator Prototype Building was held, giving all attendees the opportunity to visit the vault and the RF area.

 

Dinner
LTM07 attendees at Japanese restaurant “Darumaya”
Hirosaki
Cherry blossom, Hirosaki (Japan)

 

 

 

 

 

 

 

 

 

A pleasant event on the second day of the meetings was organized in a typical Japanese Restaurant in Rokkasho called “Darumaya”.

See you next LTM08 in Garching!

LTM08 will be held on Tuesday 24th, Wednesday 25th and Thursday 26th of November 2015.

Visit of prof. G. Rostagni and Dr. R. Piovan in Rokkasho (Japan)

LIPAc main entrance, group photo

Prof. G.Rostagni, former RFX president and historical member of BA SC (Broader Approach Steering Committee) and Dr. G. Piovan, RFX director, visited Rokkasho on 23rd October 2015. Prof. G. Rostagni is our most senior supporter, following various attempts to visit Rokkasho, it has been possible his visit after almost 7 years from the last time at Rokkasho

Visit to Vice Mayor
Greeting to the Deputy Mayor, Susumu Hashimoto-san

The agenda of the meeting was eventful, started with the greeting visit to the deputy mayor of Rokkasho Susumu Hashimoto-san accompanied by G. Pruneri, K. Sakamoto and K.Hirata respectively; Section leader ILIC Unit, deputy IFMIF/EVEDA Project Manager and JAEA site Public Affair Manager.

To follow, chronologically, were visited: Japan Nuclear Fuel Limited Facility (JNFL), Wind Power Generation System and Solar Power Generation System, all facilities are located within Rokkasho area. Lunch took place at Rokka Pokka, the famous SPA in Rokkasho.

In the afternoon were made some presentations by K. Tobita (IFERC Director) on IFERC status and future plan, G. Pruneri and K. Okiai, respectively on IFMIF/EVEDA status and the introduction of activities foreseen by JAEA, for a post BA project (A-FNS)

Afterwards took place a visit to the LINAc Accelerator, Computer Center and Demo R&D Center, with a comprehensive detailed explanation of the facilities, respectively given by K. Sakamoto-G.Pruneri, Y. Ishii-K.Tobita and H. Tanigawa – S. Nakamichi

Visit to Computer Center
Visit to Computer Center
Visit to LINAc_2
LIPAc (RF Power Supply Area)

Finally the visit ended at Misawa, to the Takara-sushi restaurant for a dinner, with a very delicious food and with a pleasant attendance of BA activities’ management: S. Ohira, K. Sakamoto, K.Tobita, K. Okumura, K. Ochiai, G. Pruneri and F. Scantamburlo.

8th LIPAc Technical Meeting

LTM08 - Participants, Garching - Germany (Group photo)
LTM08 – Participants, Garching – Germany (Group photo)

The 8th LIPAc Technical Meeting (LTM08) was held at the Garching antenna of Fusion for Energy (F4E) from 24th to 26th November 2015. More than 30 experts from different involved institutes, including CEA (Saclay, France), INFN (Legnaro, Italy), JAEA (Rokkasho, Japan), CIEMAT (Madrid, Spain), F4E (Garching, Germany) and the IFMIF/EVEDA Project Team; attended the meeting. In addition, Japanese experts from KEK and J-PARC were invited to attend on behalf of JAEA.
The first day was devoted to satellite meetings where the cryomodule assembly and licensing; and the control system were discussed in detail.

Detailed technical information was presented highlighting the significant progress that has been made for the manufacture and installation of various components since the previous LTM07 (held in Rokkasho on 15-17 June). The progress on Injector commissioning, as shown by the Deputy Director of the Department of Fusion Reactor Materials research at the JAEA Rokkasho Fusion Institute, Keishi Sakamoto, on behalf of Yoshikazu Okumura, the Head of the ILIC unit; was warmly appreciated.

Key activities which were completed on site during 2015 include:

  • 29 June  : Establishing the radiation controlled area
  • 7   July  : 1st D+ beam
  • 15 July  : Facility inspection
  • 1   Sep  : 1st arrival of the RF module to Rokkasho
  • 9   Sep  : Start phase A-2
  • 22 Oct  : Injector LCS upgrade
  • 9-13 Nov : Injector resistor repair

The main outcomes presented during the meeting are listed below:

  • Injector

Injector commissioning resumed on 22nd April, and the first deuterium beam was produced two months later on 22nd July 2015 after receiving the authorization from the Regulatory Authority on 15th July. With the change of the plasma electrode aperture diameter from 10 mm to 12 mm, a 100keV/145mA/9.5% Deuteron beam was produced. The upgrade and integration of the Local Control System into Central Control System was completed on 23rd October.

  • RF power systems

Installation of seven HVPS’s and two RF modules for the RFQ, transformers and the HV breakers on the electrical platform was nearly completed. While the activity continues, there has also been much progress in the installation of cable trays inside the RF area.

  • RFQ

The RFQ will be shipped from Legnaro (Italy) to Japan by air freight by the end of January 2016, while the associated cooling skid, piping and accessories will be shipped during December 2015. All remaining components will be shipped to Rokkasho by the end of April 2016.

On behalf of JAEA, Feedback was provided by Morishita-san explaining his experience of RFQ construction, installation and commissioning at J-PARC in Japan.

  • MEBT

With the exception of the second buncher, for which the tests are ongoing, all MEBT subcomponents have passed their acceptance tests. The assembly of the subcomponents is approaching completion, and it is expected that the complete MEBT will be sent to Rokkasho by the end of January 2016.

  • LPBD

Manufacture of The LPBD is underway, and will be completed in early 2016.

  • SRF Linac

Manufacturing contracts for all critical components have been placed, and the tender process for a number of non-critical-path items has started. Licensing activities for the complete cryomodule continue, and informal approval for the cavity design has been given by KHK. Formal approval is expected soon.

Sakai-san (KEK) presented KEK’s experience of installation and commissioning of the cERL SRF LINAc. While the cERL LINAc is fundamentally different to IFMIF / EVEDA’s, the presentation provided useful insight which will be considered as the detailed cryomodule assembly procedure is developed.

  • D-Plate

Assembly of the D-plate is nearing completion, and the fully integrated and aligned assembly will be ready for shipment at the end of January 2016.

  • HEBT/Beam Dump

The water cooling skid was recently tested and is now ready for shipment. Preparation of the shipping contract is underway, and the skid will be shipped by the end of December 2015. The main components of the Beam Dump conceptually designed and the detailed design is progressing. Technical specifications for a number of HEBT components are nearing completion and several manufacturing contracts have been launched, particularly electro deposition for the inner cone which started in November 2015

  • PPS-MPS

The Personnel Protection System has been modified to comply with regulatory requirements. The Machine Protection System has been enhanced to comply with the evolving operational requirements for injector commissioning. The Injector LCS has been fully integrated into the CCS.

A pleasant event on the second evening of the meetings was held at restaurant “Maisberger hotel” at Neufahrn

See you at the next LTM09 in Rokkasho (Japan)!

7th IFMIF Workshop held in Brasimone on 20, 21 and 22 May

Our 7th IFMIF Workshop took place during three days the 3rd week of May in Brasimone under the warm host of ENEA.

The scenarios we are living, with DONES in Europe and A-FSN in Japan being discussed, allows to state that this has been our last, so called, IFMIF Workshop, what does not mean that future similar encounters will take place.

The technical discussions were intense and fruitful, also were the unforgettable gastronomical satellite meetings organized by Gioacchino.

7th IFMIF Workshop@Brasimone, May22-22

Visit of Spanish Scientific Counsellor to Rokkasho

The Spanish Scientific Counsellor, Santiago Herrero Amigo, visited Rokkasho on 7 September and witnessed the recently arrived components of the RF Power system, one of the various top technology hardware of Spanish contribution to LIPAc.

In the afternoon, he had an official encounter with Mamoru Toda, the mayor of Rokkasho, accompanied by IFMIF/EVEDA Project Manager, Shigeru O’hira and IFMIF/EVEDA Project Leader, Juan Knaster.

 

Official encounter at Rokkasho village

 

 

 

 

 

 

 

 

 

 

 

 

 

Photo taken at Rokkasho Village Office on September 7, 2015

 

 

 

 

Delivery of the first components of the LIPAc’s RF Power System

 

We are proud to announce that the first components of the LIPAc’s RF Power System have arrived at Rokkasho site.

After a long sea travel from Spain, three containers reached Hachinohe port on 28th August. Devanning at the port and transportation from Hachinohe to Rokkasho took three days starting from 31st August.

 

RF Delivery_Containers  RF Delivery_TruckContainers at Hachinohe Port (left); and truck loaded and ready to depart to Rokkasho (right)

 

 

A total of fifteen packages were delivered to Rokkasho site; including seven RF high voltage power supplies (HVPS), two RF Modules, three electrical distribution cabinets, and auxiliaries.

From 2nd to 4th September, NKK Company opened all the wooden crates and started the installation of the components, which is expected to be completed by the end of the month.

RF Delivery_3  RF Delivery_RF Modules RF Power System’s wooden crates staged at the RF Power Bay Area (right) and two RF Modules (main and circulator platform) ready for its installation (right)

 

 

 

 

Japanese Postman

JapanesePostman
Japanese Postman

After almost five years since we arrived in Japan, my wife and I continue to astonish ourselves for the attractiveness and oddities that surround us.
We were impressed of the simplicity, morality and straightforwardness of the Japanese people; even though various events of daily life are often diametrically divergent and sometimes appear to me strange compared to the standards and customs of my home country, Italy.
For instance, it was a surprise to me to see the Japanese postman delivering the mail during wintertime; this might be normal worldwide, but in Japan, the peculiarity is that the postman delivers mail during winter, driving a motorcycle even during heavy snowfalls, with roads covered in white and slippery snow, and often icy!  Saturday and Sunday they still work regularly, 365 days per year the service is available and very efficient.
In Italy, Postmen use as well the motorcycle or bike, season allowing, normally is preferable a small car.