After completing the first beam operation stage, and while profiting of the stop of the machine for the scheduled maintenance, the first LIPAc Commissioning and Beam Operation workshop was organized at Rokkasho site.
During 2 days, the accelerator scientists and experts from Japan and Europe exchanged about the experiences and outcomes of the first beam operation campaign with the LIPAc RFQ accelerator, and the difficulties encountered in the LIPAc commissioning activities. Discussions also addressed the preparation of the second beam campaign, scheduled from early next year. Furthermore, the steps ahead were discussed to prepare the assembly, installation and commissioning of the last accelerating stage (including the superconducting cavity SRF Linac, which will increase the deuteron energy up to 9MeV).
The next workshop with a similar format will gather again the LIPAc community after the completion of the commissioning Phase B (5 MeV, 125 mA, D+,0.1% DC, including the commissioning of the RFQ and Buncher cavities, as well as the beam instrumentation).